Pulliam Power Plant NPDES Permit Appeal

Sierra Club
Project completed June 2015

Synapse assisted Sierra Club with an analysis of the revenue requirements necessary to install a cooling tower at Wisconsin Public Service Corporation?s (WSPC) Pulliam Units 7 and 8. Rachel Wilson submitted direct testimony to the Wisconsin Division of Hearings and Appeals on total cost estimates for construction and operation of the cooling towers as well as the economic achievability of the cooling towers and the expected impact on electric rates in WSPC?s service territory.