Technical and Regulatory Support to the Newfoundland and Labrador Board of Commissioners of Public Utilities
Newfoundland and Labrador Public Utilities Board
Project Complete
Synapse was engaged by the Newfoundland and Labrador Board to provide detailed technical support during a first-phase review of “rate mitigation” approaches associated with the impending start-up of the Muskrat Falls hydroelectric generating station in Labrador. Synapse evaluated the Province’s load forecast, the potential for beneficial electrification and more aggressive energy efficiency policies, and the amount of surplus energy available for export. Synapse also addressed time-of-use and related rate design issues, and provided a more in-depth analysis of all issues during a second phase of work in 2019.